|
|
|
Staging Map of 2008 Projects- mouse over yellow stars and arrows on map for brief project info. HTHW (High Temperature Hot Water) Line Replacement Phase II This project involves replacing aging high temperature hot water lines at various locations around campus. Please note that East Drive is scheduled to be closed May 27 through June 9 during Phase C.
**UPDATE: East Drive near the Administration Building will be closed May 27 until June 9. Traffic will be detoured during this portion of the work. Signs will indicate the detours.**
University Union Renovation Phase 1 This project will begin after Commencement in May 2008. In the week after Commencement, furniture and other items still remaining in building will be moved to storage. Fencing and staging areas will be established. The first part of the project involves asbestos abatement. This is scheduled to begin May 27. The asbestos removal will continue through the summer and renovations will follow beginning late fall, 2008. Spaces being renovated include UU 133, the Mandela Room, Old Union Hall, several meeting rooms, lounges, the Tillman Lobby and the floors above and below those spaces. Work includes new ceilings, lighting, finishes, heating, ventilation and air conditioning systems, new power distribution, sprinklers and smoke detectors. A skylight will be installed in the Tillman Lobby, a new waiting area enclosure will be constructed for bus users and a number of multi-purpose rooms will be created as a result of the project. The renovations are scheduled to be complete in August, 2009. University Union Roof Replacement The roof over a portion of the south half of the University Union will be replaced in summer 2008. The work will begin following Commencement and take about two months to complete. Engineering Building Critical Maintenance Beginning Monday, May 19, a floor removal/asbestos abatement project will begin in the Engineering Building. The project will affect a number of areas at different times over the summer. Some areas will not be accessible for short periods of time. Building maps indicating work areas have been posted in the departments. Signage will also be used to get people around work areas. The scope of work includes removal of asbestos containing floor tiles along with ceiling, lighting, flooring and door replacements. General upgrades to corridors, classrooms and other spaces is also part of the project. Susquehanna Community Gas Main A gas main will be installed in the Susquehanna Community so that hot water heaters can use natural gas instead of electricity to help improve efficiency. Work will begin May 19 and be complete this summer. East Campus Housing (ECH)- Building 1
Work hours on the site are 7 a.m. to approximately 5 p.m. Trucks and other construction vehicles will access the site via Center Drive and East Drive. More info Some parking changes have been implemented due to the project and more detail and maps regarding the changes can be found here. The building will house 341 students. This floor plan shows the layout of floors 2 through 5. The first floor including a great room, laundry facilities and Residential Life offices can be seen in this floor plan. Building features include:
The completion date for the first building is August 2009.
The overall site plan for the entire Newing College and Dickinson Community replacement can be seen here. A timeline for the entire project is also available. Memorial Courtyard The contractor has begun additional renovations in the Memorial Courtyard. Work includes installing new walkways and landscaping. HTHW (High Temperature Hot Water) Line Replacement Phase I This project began last year and involved replacement of HTHW pipe in the Science I/II courtyard. The remaining piece of the project involves installing HTHW piping in the area of the Physical Facilities compound. Work began March 17th in the area in front of the garage. Traffic in the compound is restricted in the work area. Work is expected to be complete around the second week in June. Electrical Distribution Upgrade Phase 1 A new electrical duct bank system will be installed from the switch yard in the Physical Facilities compound and along West Drive from the Academic Complex to Science III/IV. The work will involve digging a trench and installing a duct bank which will house new electrical cables. Old electrical cables will be replaced and the project will help feed new buildings such as Science V and East Campus Housing. The project will also help the campus better balance electrical loads, provide redundancy to the electrical infrastructure and allow for easier maintenance of the system. The project is scheduled to start in late July and be complete in December. Water Softener Installation A small building will be constructed next to the Pump House on the perimeter of parking lot E to house new water softening equipment. It will house three tanks and storage space for rock salt which is used in the water softening process. The project is now underway and will be complete in November. Newman Pedestrian Bridge Renovation The pedestrian bridge linking the campus to the Newman House will be renovated in summer 2008. Work is expected to start in June and be complete in August. The bridge will be closed during that time but pedestrians may cross the creek using the bridge to the Innovative Technologies Complex. Library Tower Refurbishments Phase 2 Offices on floors 6-9 will be refurbished. The work includes cleaning fin tubes (heating elements), caulking windows, painting, floor cleaning an installing new furniture.
Bunn Hill Entrance Sign Work is underway to install a message board at the Bunn Hill campus entrance. The message board that will be put in place is similar to the one installed at the main campus entrance. Susquehanna Community Kitchen/Bath Renovations The kitchens and baths in Nanticoke and Choconut will be renovated in summer 2008. New cabinets, countertops, sinks, ceiling lights, tub surrounds, lavatories, toilets and flooring are included. The construction will start after Commencement and be complete by the time students return in August. This project is similar to the renovations that took place last summer in Brandywine and Glenwood. Residential Hall Fire Alarm Upgrades Fire alarm systems will be enhanced in all buildings in the Hillside Community except Rockland and Saratoga and also in Mountainview's Hunter and Marcy Halls. The work will start following Commencement and be complete before students return in August. CIW-Seneca Abatement/Renovations Materials containing asbestos will be removed. New ceilings, flooring, carpeting and energy efficient lighting will be installed. New furniture is also part of the project. The work will take place following Commencement and be complete when students return. |
Send mail to the
Webmaster with questions or comments about this website.
|